Project Milestone

Milestone – CA relatedDate
Signing of Concession Agreement4th Aug 2017
Financial Closure and Award of Concession19th Apr 2018
Milestone – Contracts and Execution RelatedDate
Appointment of DESIGN Engineers and PMC (M/s LNTIEL)7th Sep 2017
Appointment of Independent Engineer (RITES)2nd Jan 2018
Award of Contract for construction of Berth, Short arm Wall and Retaining structures (L&T Geostructures)24thApr 2018
Completed date of Berth, Short arm Wall and Retaining structures9th Nov 2019
Issue of Letter of Award for EPC for Electro Mech and associated Civil works (ISGEC)15th Aug 2018
Milestone dateActivity/Level of Completion of Project.
365 days from Date of Award of Concession (4th Aug 18)2.40%
730 days from Date of Award of Concession (4th Aug 19)44.50%
1096 days from Date of Award of Concession (4th Aug20)84.14%
1944 days from Date of Award of Concession (30th November 22)99.35%